Stream Restored: ~3,650 feet
Planting Stats:  7,240 (live stakes), 1,256 (trees)
Carbon Sequestration:  32.1 tons
Sediment Reduction: 220 tons

Resource Institute’s Partners:

Natural Resource Concerns/Issues

  • Streambanks on Line Creek were steep and severely eroded and lacked a riparian buffer

  • Original Stream = Type G4c

Project Objectives:

  • New Stream Type = B4c

  • Improve water quality by reducing sediment, nutrient, organic, and inorganic loading of the stream and reduce streambank erosion

  • Stabilize the stream reach to prevent further aggradation or degradation by providing an improved dimension, pattern and/or profile that will improve sediment transport and manage surface waters and groundwater levels in floodplains, riparian areas, and wetlands

  • Construct rock and woody structures to provide instream habitat, stabilize streambanks and the channel bed

  • Establish a riparian buffer, remove invasive plant species, and reestablish native plants, trees, and shrubs