LEWIS CREEK STREAM RESTORATION PROJECT

HENDERSONVILLE, NC

STATS

French Broad Watershed
Henderson County, Hendersonville, NC

  • STATUS: COMPLETED 2023
  • APPROX. 3,020 FEET OF STREAM RESTORED
  • PLANTING STATS: 3,900 LIVES TAKES & 2,600 TREES
  • CARBON SEQUESTRATION - 85.1 TONS (OVER 10 YEARS)
  • SEDIMENT REDUCTION: 180 TONS
lewis creek stream restoration project before
lewis creek stream restoration project after
BEFORE
AFTER

Natural Resource Concern/Issues

  • Streambanks on Coon Branch & UT Lewis Creek were steep and severely eroded and lacked a riparian buffer

  • Original Stream = Type G4c

Project Objectives:

  • Restored Stream Type = C4

  • Improve water quality by reducing sediment, nutrient, organic, and inorganic loading of the stream and reduce streambank erosion

  • Stabilize the stream reach to prevent further aggradation or degradation by providing an improved dimension, pattern and/or profile that will improve sediment transport and manage surface waters and groundwater levels in floodplains, riparian areas, and wetlands

  • Construct rock and woody structures to provide instream habitat, stabilize streambanks and the channel bed

  • Provide an alternate watering source for livestock, including a pump and livestock pipeline to convey water to watering facilities and protect the surrounding heavy-use area.

  • Install fencing to restrict livestock access to the stream corridor to protect streambanks and streambank vegetation

  • Establish a riparian buffer, remove invasive plant species, and reestablish native plants, trees, and shrubs