Line Creek Stream Restoration Project
Line Creek
French Broad Watershed, Mills River
Henderson County, Hendersonville, NC
Status: Completed 2023
Stream Restored: ~1,050 feet
Planting Stats: 2,000 live stakes and 290 trees
Carbon Sequestration - 17 tons in 10 years
Sediment Reduction - 88 tons
Resource Institute’s Partners:
Natural Resource Concern/Issues
-
Streambanks on Line Creek were steep and severely eroded and lacked a riparian buffer
-
Original Stream = Type CG4c
Project Objectives:
-
Restored Stream Type = C4
-
Improve water quality by reducing sediment, nutrient, organic, and inorganic loading of the stream and reduce streambank erosion
-
Stabilize the stream reach to prevent further aggradation or degradation by providing an improved dimension, pattern and/or profile that will improve sediment transport and manage surface waters and groundwater levels in floodplains, riparian areas, and wetlands
-
Construct rock and woody structures to provide instream habitat, stabilize streambanks and the channel bed
-
Provide an alternate watering source for livestock, including a pump and livestock pipeline to convey water to watering facilities while protecting the surrounding heavy-use area
-
Install fencing to restrict livestock access to the stream corridor to protect streambanks and streambank vegetation
-
Establish a riparian buffer, remove invasive plant species, and reestablish native plants, trees, and shrubs